Motion to Reject Untimely Comments in RM21-17
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION
Building for the Future Through Electric Regional Transmission Planning and Cost Allocation and Generator Interconnection, Docket No. RM21-17-000
MOTION TO REJECT UNTIMELY SUPPLEMENTAL COMMENTS, OR IN THE ALTERNATIVE, TO ACCEPT SUPPLEMENTAL COMMENTS OF THE NEW ENGLAND STATES COMMITTEE ON ELECTRICITY
Pursuant to Rule 212 of the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) Rules of Practice and Procedure, 18 C.F.R. § 385.212, the New England States Committee on Electricity (“NESCOE”)[1] respectfully requests that the Commission reject the untimely[2] supplemental comments[3] filed in the above-referenced docket. If the Commission accepts the various untimely supplemental comments, in the alternative, NESCOE respectfully requests that the Commission accept its own supplemental comments.
I.