Renewable Resource Request for Information – Supplemental Information
…
…
…
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION
Midwest Independent TransmissionSystem Operator Inc.
Docket No.
New England States Announce Next Step To Facilitate Development of the Region’s Renewable Resources Able to Serve Customers Most Cost-Effectively
November 16, 2010 – The New England States C…
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION
Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities
Docket No.
NESCOE Responses to Issues Raised Regarding Tie Benefits Design Basis Document
October 7, 2010
The Tie Benefits Design Basis Document (DBD) adopted at the September 22, 2010 Reliability Committee remo…
NESCOE Clarification: Tie Benefit Design Basis Document Reserve Requirement
October 6, 2010
The New England States Committee on Electricity (NESCOE) provides this memorandum to clarify an issue concer…
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION
Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities
Docket No.
To: Mike Henderson, ISO-NE
From: NESCOE
RE: Additional Analysis on Needs Assessment
Date: September 20, 2010
Following ISO-NE’s NEEWS, Interstate Reliability Project Needs Reassessment pre…
…