Memorandum Regarding NEEWS-IRP Needs Reassessment
To: Mike Henderson, ISO-NE
From: NESCOE
RE: Additional Analysis on Needs Assessment
Date: September 20, 2010
Following ISO-NE’s NEEWS, Interstate Reliability Project Needs Reassessment pre…
To: Mike Henderson, ISO-NE
From: NESCOE
RE: Additional Analysis on Needs Assessment
Date: September 20, 2010
Following ISO-NE’s NEEWS, Interstate Reliability Project Needs Reassessment pre…
…
INITIAL INPUT OPPORTUNITY COORDINATED RENEWABLE PROCUREMENT
September 2010
Update – Responses Received:
ISO New England
Anbaric Transmission
Joint New England Transmission Owners
NStar
United I…
To: Michael Henderson, ISO-NE & the Planning Advisory Committee
From: New England States Committee on Electricity
Date: August 5, 2010
Re: Comments on Draft Regional System Plan, 2010
The New Engl…
…
…
To: Mike Henderson, ISO-NE
From: New England States Committee on Electricity
Re: Draft Assumptions, 2010 Economic Study
Date: July 1, 2010
CC: ISO-NE Planning Advisory Committee
Pursuant to discussio…
June 25, 2010
Mr. David Meyer
U.S. Department of Energy
Office of Electricity Delivery and Energy Reliability
1000 Independence Avenue, SW
Washington, DC 20585
Dear Mr.
…
…