Transmission in the Northeast: Law Seminars International
March 20, 2015
Overview
Transmission in New England
- Congestion
- Other resources delaying or replacing transmission
- Planning Guides
- Cost Estimating and Containment
- Order 1000
New England Governors’ Infrastructure Initiative
CONGESTION VIRTUALLY NON-EXISTENT
“The…2009 Congestion Study concluded that New England was no longer a Congestion Area of Concern. Since that time, congestion in New England has diminished even further and is today virtually non-existent.” NESCOE Comments to 2012 National Electric Transmission Congestion Study, U.S. DOE Consultation Draft
Looking back 2002 – June 2014: 559 projects into service –
$6.6 billion new infrastructure investment
Looking ahead: As of June 2014, the total estimated cost of transmission upgrades – proposed, planned, under construction – was approximately $4.5 billion
SIGNIFICANT STATE INVESTMENT IN OTHER RESOURCES THAT REDUCE THE NEED FOR OR AFFECT TIMING OF NEW TRANSMISSION TO MEET RELIABILITY NEEDS
DISTRIBUTED GENERATION
- ISO-NE developed, at states’ request, solar PV forecast based on state policies with funding sources
- With discounts, region expects to increase installed solar from roughly 175 MW in 2013 to almost 500 MW by 2016 and up to almost 750 MW by 2024
- In 2014 forecast of solar PV as to the end of 2014, ISO- NE projected 246.5 MW of new solar PV; survey indicates actual increase was 410 MW
- ISO-NE collecting data on DG more broadly for forecast
ENERGY EFFICIENCY
- Four New England states – MA, CT, RI, VT
– in top 10 nationally for EE - Aggressive investment is reflected in regional planning, at states’ request
- 2018-2023 ISO-NE EE Forecast shows MA will invest another $3B over time period – savings of at least 4.5 TWh and 605 MW
- New England states will invest $5.7 billion for total savings of 9.1 TWh and 1.2 GW by 2023
TRANSMISSION PLANNING GUIDES
In response to states’ request, ISO-NE developed Transmission Planning Guides on the regional planning process and planning assumptions
- increase transparency about and confidence in aspects of planning questioned by stakeholders and in state siting
- memorializes what are reasonable assumptions and criteria ISO-NE uses to model transmission system conditions in identifying a “need”
Multi-year Road to Consider Use of Probabilities in Planning
a more analytical, mathematical approach to developing assumptions
2013: NESCOE presented in several venues the concept of using probabilities in planning
2014: ISO-NE began stakeholder discussions
2015: New England will begin examining load modeling and unit availability
assumptions
TRANSMISSION COST ESTIMATES & CONTAINMENT
Reliable transmission project cost estimates are a prerequisite to ISO-NE’s and state siting authorities’ assessment of alternative means to satisfy an objective in a way that best meets consumer interests
Competitive dynamics under FERC Order 1000 spotlights this challenge States are interested in appropriately structured cost containment as:
- a tool to limit the risk of cost overruns
- a selection criterion for evaluating competing transmission projects
- a way to balance consumers’ interest in cost certainty and transmission developers’ legitimate unforeseeable transmission project costs
In 2015, NESCOE will encourage focus on cost containment approaches, including cost caps and a review of the process for developing transmission project cost estimates
FERC issued latest ruling in New England’s Order 1000 March 19th
Public Policy in Planning
- States: differing views
- Shared view on strong state role
- It’s one tool for states, per FERC
- Some states interested in considering options to satisfy their state policy objectives through incremental transmission already working regionally and already moving to consider resources and infrastructure; some states all set
Competitive Transmission
- States: common positive view
- Complexity in implementation
- Complexity in comparing competing projects with different benefits and challenges
- Critical to get details right to achieve potential consumers benefits
- Accurate cost estimates
- Reasonable study parameters and costs
Public policy consideration can’t just be about poles and wires: wholesale markets need to accommodate resources required by state laws
Developers should resist temptations to turn this into a lobbying or PR exercise: it’s all about objective analysis by ISO-NE and before state siting authorities
Multi-state Coordinated Clean Energy RFP
Certain state agencies and utilities in CT, MA and RI developed, with NESCOE assistance, a joint RFP for clean energy projects based on each state’s current authority. www.CleanEnergyRFP.com
Objective: To explore whether a multi-state procurement might attract larger-scale projects and transmission than single state procurements and achieve individual states’ clean energy goals more cost effectively than if each state proceeded on its own
Feb 25 • Issue draft RFP for public comment
March 27 • Public Comment due
Spring 2015 • Expected issuance
Clean Energy RFP: Eligibility and Mechanics
- Resource Types: Class I renewable power (wind, solar) or large-scale hydro meeting requirements of states’ laws. 20 MW minimum threshold. Over 2,000 GWh in total.
Project types
- Traditional PPAs No Transmission Requirement
- PPAs with associated Transmission
- Clean energy delivery commitments
Clean energy delivery commitment proposals tie transmission-only support payments to the project’s performance in fulfilling the commitments for the delivery of clean energy
- Support payments under a FERC filed and accepted transmission tariff/rate schedule paid for by the participating states
RFP issuers will jointly and individually evaluate bids
- No obligation to procure anything at all
Each state, EDC use own authority, criteria, judgment to determine whether a proposed project is cost-effective and beneficial for its consumers
New England Governors’ Energy Infrastructure Initiative
Strategic, coordinated investments in regional energy infrastructure
that would
Improve energy system reliability
Diversify our energy supply portfolio
Strengthen state and regional economic competitiveness
Meet common energy and environmental policy goals
Increase the supply of cleaner, no-to-low carbon generation
Mitigate energy price volatility
Achieve what no single state could do on its own Consumer benefits must outweigh consumer costs
Market-Based Pipeline Solutions Not Meeting New England’s Needs
Gas and Electricity Markets’ Term Mismatch
Nationally, the natural gas pipeline industry is based on long-term contractual commitments (i.e., at least 10 years, commonly 15-20 years)
In New England, the electric industry is based on short-term market price signals (up to seven years for new resources, year-to-year for existing)
Recent pipeline projects in New England have had zero electric power generators subscribe for firm natural gas transportation
Spectra’s AIM project was downsized from original design due to lack of subscription from 500 mmcf/day to 342 mmcf/day
Consumer Consequences of Constraints
U.S. Department of Energy EIA
New England price increases triple the national average increase in first half of 2014 compared to first half of 2013
Retail Rate Increases – Energy Only
Per Eversource 11/ 2/ 14 presentation
Power System Reliability Consequences of Constraints
“The challenges to grid reliability are not a question of if they will arise, but when – and when is now.” ISO-NE 2014 Regional Electricity Outlook
“The performance of the largest and most flexible portion of the region’s generating fleet is being weakened by insufficient natural gas pipeline and LNG storage in the region.” ISO-NE 2015 Regional Electricity Outlook
WINTER RELIABILITY PROGRAMS
- Out of market investment primarily in oil credited with sustaining power system reliability over the last two winters
- ISO-NE identifies reliability need for future Winter Programs
- Costs to consumers of future programs must be benchmarked against costs of current winter program
Emissions Consequences of Constraints
New England relying more heavily on oil & coal resources
- At times this winter they represented about 45% of generation
- New England used 7 million barrels of oil in the 2014/15 winter reliability program
ISO-NE 2015 Regional Electricity Outlook
“When gas-fired generators are unavailable to run or underperform, the ISO may need to commit significant amounts of additional generating resources—mostly oil and coal plants—to maintain system reliability.”
“There’s an environmental cost when the region can’t use its gas-fired units to meet demand. Higher-emitting oil- and coal-fired plants run more often instead, leading to increases in regional air emissions.”
Some argue that states’ interest in solving infrastructure constraints was a reaction to last year’s historic prices, and that New England’s power system challenges are resolved because this winter, prices did not exceed last years’ historic highs.
According to U.S. DOE’s EIA:
- Natural gas prices in New England during the week of February 15, 2015 were more than 10 times the price in Pennsylvania and 5 times the price at the Henry Hub
- As of January and February of 2015, New England electricity and natural gas prices were almost twice as high as the Mid-Atlantic and four times higher than other parts of the country
Actions, Late 2014
- July 31, 2014: Massachusetts Legislature adjourned without acting on a bill to enable the state to procure levels of no-and/or low- carbon power
- August 1, 2014: NESCOE requested from NEPOOL a pause in discussions to provide Massachusetts state officials time to evaluate options
- Fall – December 2014: Massachusetts undertook further study of Massachusetts state-level solutions in light of state policies in December 2014, which, like the myriad studies on the subject, identified a need for additional natural gas pipeline capacity
Some Current Activities
- State officials continue discussing ways forward on regional solutions
- Governors discussed New England energy challenges in November, plan to resume discussion in April
- Some parallel state activities:
- Multi-state clean energy solicitation
- Connecticut DEEP issued IRP identifying resource needs
- associated legislation pending
- Maine and Rhode Island have enabling laws
- Maine PUC proceeding to evaluate gas pipeline proposals ongoing
- Massachusetts DPU to consider electric company authority under current law to support incremental natural gas pipeline for electric power system purposes
- separately, broad legislative proposals under discussion