NESCOE

Order 1000 Appeal to D.C. Circuit – Reply Brief

Legal Document

Dated: April 22, 2016

Posted in:

Authored by:

Oral Argument Has Not Yet Been Scheduled
Nos. 15-1139 and 15-1141 (consolidated)
________________________________________________________________

UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT
____________

Emera Maine, formerly known as Bangor Hydro-Electric Company, et al., Petitioners in 15-1139
New England States Committee on Electricity, Inc., et al., Petitioners in 15-1141

v.

Federal Energy Regulatory Commission, Respondent
LS Power Transmission, LLC, et al., Intervenors
____________

On Petition for Review of Orders of the Federal Energy Regulatory Commission

____________

REPLY BRIEF FOR PETITIONERS IN NO. 15-1141

John Michael Adragna
Phyllis G. KimmelJeffrey K. Janicke
McCarter & English, LLP
1015 Fifteenth Street, N.W., 12th Floor
Washington, DC 20005
(202) 753-3400

pkimmel@mccarter.com

Attorneys for New England States Committee on Electricity, Inc.

April 22, 2016

Jason Marshall
General Counsel
New England States Committee
on Electricity, Inc.
655 Longmeadow Street
Longmeadow, MA 01106
(617) 913-0342
jasonmarshall@nescoe.com

Attorney for the New England States Committee on Electricity, Inc.

Robert Snook, AAG
Office of the Attorney General
Ten Franklin Square
New Britain, CT 06051
(860) 827-2657
Robert.Snook@ct.gov

Attorney for the Connecticut Department of Energy and Environmental Protection

Clare Kindall, AAG
Office of the Attorney General
Ten Franklin Square
New Britain, CT 06051
(860) 827-2683
Clare.kindall@ct.gov

Attorney for the Connecticut Public Utilities Regulatory Authority

Maura Healey
Massachusetts Attorney General
Cecile M. Fraser, Counsel
Special Assistant Attorney General
Jeffrey M. Leupold, Senior Counsel
Massachusetts Department of Public Utilities
One South Station, Fifth Floor
Boston, MA 02110
(617) 305-3621
Cecile.Fraser@state.ma.us
Jeffrey.Leupold@state.ma.us

Attorneys for the Massachusetts Department of Public Utilities

 

F. Anne Ross
General Counsel
New Hampshire Public Utilities Commission
21 South Fruit Street, Suite 10
Concord, New Hampshire 03301-2429
(603) 271-2431
f.anne.ross@puc.nh.gov

Attorney for the New Hampshire Public Utilities Commission

Leo J. Wold
Assistant Attorney General
150 South Main Street
Providence, RI 02903
(401) 274-4400, ext. 2218
lwold@riag.ri.gov

Attorney for the Rhode Island Public Utilities Commission

Edward McNamara
Regional Policy Director
Vermont Department of Public Service
112 State Street
Montpelier, VT 05620
(802) 828-4007
ed.mcnamara@state.vt.us

Attorney for the Vermont Department of Public Service

__________________________________________________________________

TABLE OF CONTENTS

TABLE OF CONTENTS. i

TABLE OF AUTHORITIES. ii

GLOSSARY.. iii

SUMMARY OF ARGUMENT. 1

ARGUMENT. 3

I………….. FERC Has Substantively Failed to Rebut the States’ Argument that the Challenged Orders Expanded the Requirements of Order No. 1000. 3

  1. The States’ Threshold Issue for Review Is FERC’s Unlawful Expansion of Order No. 1000 by Requiring Project Selection. 3
  2. FERC’s Claim That the Challenged Orders Did Not Require Project Selection Is Contrary to the Very Language of those Orders and Is Contradicted by the Mechanisms It Has Required ISO-NE to Employ. 5

II……….. FERC’s Undisputed Authority over Interstate Transmission Planning and Cost Allocation Does Not Give FERC License to Decide how State Policies Should Be Implemented. 10

  1. Contrary to FERC’s Characterization, the Challenged Orders Require ISO-NE Selection of Transmission Projects to Meet State Public Policy Needs, Thus Requiring Substantive Outcomes and Infringing on State Authority. 10
  2. FERC’s Authority Over Interstate Transmission and Cost Allocation Does Not Grant FERC the Authority to Determine How to Implement State Public Policies. 15

CONCLUSION.. 20


 

TABLE OF AUTHORITIES

Court Cases

FERC v. Elec. Power Supply Ass’n,
136 S. Ct. 760 (2016)………………………………………………………… 18, 19, 20

Oneok, Inc. v. Learjet, Inc.,
135 S. Ct. 1591 (2015)……………………………………………………………. 18, 19

*S.C. Pub. Serv. Auth. v. FERC,
762 F.3d 41 (D.C. Cir. 2014)………………………………………………. 2, 6, 9, 17

Statutes

Administrative Procedure Act,
5 U.S.C. § 553……………………………………………………………………………. 2

Federal Power Act,
16 U.S.C. § 791a, et. seq.…………………………………………………….. 2, 10, 13

16 U.S.C. § 824(a)……………………………………………………………………… 17

Regulations

*Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities, Order No. 1000, FERC Stats. & Regs. ¶ 31,323, 76 Fed. Reg. 49,842 (Aug. 11, 2011), order on reh’g, Order No. 1000-A, 139 FERC ¶ 61,132, 77 Fed. Reg. 32,184 (May 31, 2012), order on reh’g and clarification, Order No. 1000-B, 141 FERC ¶ 61,044, 77 Fed. Reg. 64,890 (Oct. 24, 2012), aff’d sub nom. S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41 (D.C. Cir. 2014)…………………………………… 1, 2, 3, 4, 5, 6, 9, 13, 16, 17, 20

*Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities, Order No. 1000-A, 139 FERC ¶ 61,132, 77 Fed. Reg. 32,184 (May 31, 2012) (“Order No. 1000-A”), order on reh’g and clarification, Order No. 1000-B, 141 FERC ¶ 61,044, 77 Fed. Reg. 64,890 (Oct. 24, 2012) 1, 4

Authorities upon which we chiefly rely are marked with asterisks.


GLOSSARY

Br.Brief
Compliance FilingOrder No. 1000 Compliance Filing of ISO New England Inc. and the Participating Transmission Owners Administrative Committee, Docket Nos. ER13-193-000, et al. (October 25, 2012), R. 1
Compliance OrderISO New England Inc., 143 FERC ¶ 61,150 (2013), R. 53
FPAFederal Power Act
FERCFederal Energy Regulatory Commission
ISO-NEISO New England Inc.
NESCOENew England States Committee on Electricity, Inc.
OATTOpen Access Transmission Tariff
Order No. 1000 Order No. 1000-ATransmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities, Order No. 1000, FERC Stats. & Regs. ¶ 31,323, 76 Fed. Reg. 49,842 (Aug. 11, 2011), order on reh’g, Order No. 1000-A, 139 FERC ¶ 61,132, 77 Fed. Reg. 32,184 (May 31, 2012), order on reh’g , Order No. 1000-B, 141 FERC ¶ 61,044, 77 Fed. Reg. 64,890 (Oct. 24, 2012), aff’d sub nom. S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41 (D.C. Cir. 2014).
Public policy requirementsThose policy requirements established by state or federal laws and regulations, including enacted statutes and regulations promulgated by a relevant jurisdiction, whether within a state or at the federal level, and including duly enacted laws or regulations passed by a local governmental entity, such as a municipal or county government.
Regional System PlanISO-NE’s determination, over a ten-year horizon, of the region’s electricity system needs and plans for meeting those needs, including a list of selected transmission facilities
Rehearing OrderISO New England Inc., 150 FERC ¶ 61,209 (2015), R. 101
State AgenciesThe Commissioner of the Connecticut Department of Energy and Environmental Protection, the Connecticut Public Utilities Regulatory Authority, the Department of Public Utilities of the Commonwealth of Massachusetts, the Rhode Island Public Utilities Commission, the State of New Hampshire Public Utilities Commission, and the Vermont Public Service Department
StatesNESCOE and the State Agencies

SUMMARY OF ARGUMENT

FERC’s brief generally repeats the arguments made in the orders below but fails to address directly the core arguments made by the States.  Instead, FERC attempts to portray the States as challenging FERC’s authority over interstate transmission.  The States have made no such argument.  The States narrowly confined their objection to a specific action that FERC took, i.e., imposing an obligation on ISO New England Inc. (“ISO-NE”) to select a public policy-driven transmission project in the Regional System Plan for cost allocation purposes.  ISO-NE must select a project unless, in a very unlikely scenario, ISO-NE were to determine that notwithstanding the highly integrated regional transmission system in New England, a local transmission project is the more efficient or cost-effective solution.[1]  Even in this unlikely case, the result is still a substantive outcome.   FERC has thus converted this component of Order No. 1000[2] from a process-only rule, under which transmission providers are required only to identify and evaluate transmission solutions to public policy needs, to one that results in the selection of a transmission project.  This selection is a critical milestone for that project to secure financing and move to the next steps of project construction.

FERC fails to rebut the States’ arguments that this action exceeds FERC’s authority under the Federal Power Act (“FPA”), as FERC may not determine how a state should implement its own public policies.  FERC also fails to rebut the States’ arguments that the challenged orders impermissibly expand the scope of the Order No. 1000 rulemaking, contrary to the Administrative Procedure Act, 5 U.S.C. § 553.  As the States demonstrated in their initial brief, FERC, without statutory authority, has stripped New England states of their ability to decide whether, how and at what cost to satisfy their own public policies and what project or projects might be the optimal or even preferred means to advance their own statutory requirements.


ARGUMENT

I.              FERC Has Substantively Failed to Rebut the States’ Argument that the Challenged Orders Expanded the Requirements of Order No. 1000.

A.           The States’ Threshold Issue for Review Is FERC’s Unlawful Expansion of Order No. 1000 by Requiring Project Selection.

The States illustrated in their initial brief (at 25-34) how the challenged orders unlawfully expanded the scope of Order No. 1000.  FERC’s brief seeks to shift the focus of the argument to which entity should select a public policy-driven transmission project (i.e., ISO-NE) and away from the real issue, i.e., whether FERC’s rulings unlawfully obligate the selection of a public policy-driven transmission project.  Br. at 3-4, 21-23, 56-59.  FERC mischaracterizes the States’ petition at the outset of its brief (at 3-4) to comport with this line of argument.  The Court should disregard this gambit.

The States demonstrated that FERC expanded the scope of the Order No. 1000 directives in a subsequent compliance proceeding by requiring, for the first time, that ISO-NE select a specific project at the culmination of the public policy planning process.  The States had asked FERC to clarify that this was not FERC’s intent (R. 26 at 22), but the Rehearing Order failed to so clarify.  Instead, the Rehearing Order included (at P 126, R. 101 at 60) a double-negative statement that can only mean that ISO-NE is required to select a transmission project in the regional transmission plan for purposes of cost allocation unless ISO-NE were to find the regional transmission solution less efficient or cost-effective than a local transmission alternative, a highly unlikely outcome in New England as explained in the States’ initial brief (at 29-30).

FERC’s arguments that ISO-NE is the appropriate entity to select specific projects to satisfy state policies ignore the fundamental unlawfulness of the agency’s expansion of Order No. 1000.  FERC includes several other statements that might also distract from the fundamental issues before the Court.  For example, FERC implies that the States are asking the Court to impose a package of proposed changes already rejected by FERC as part of the compliance process (Br. at 21-23, 55-57) and that the States are challenging FERC’s determination that ISO-NE may not delegate its obligation to evaluate potential solutions to transmission needs driven by public policy requirements (see id. at 58).  Neither proposition is correct.  The only issue before this Court is FERC’s unlawful expansion of Order No. 1000 by leaping from that order’s requirement that ISO-NE consider public policy requirements in the regional planning process (see, e.g., Order No. 1000-A at PP 320-321) to dictating a substantive outcome by imposing an affirmative obligation on ISO-NE to select a specific transmission project in the regional plan for cost allocation purposes (except, again, in the unlikely event that there is a local transmission solution that is more efficient or cost-effective than the regional transmission solution).

B.            FERC’s Claim That the Challenged Orders Did Not Require Project Selection Is Contrary to the Very Language of those Orders and Is Contradicted by the Mechanisms It Has Required ISO-NE to Employ.

FERC attempts to rebut the States’ claim that the agency impermissibly expanded Order No. 1000 by arguing that its rulings did not focus on the “outcome” of the evaluation of policy-driven transmission solutions (Br. at 22), and “did not . . . mandate that the transmission provider select a project.”  Id.; see also id. at 59.  These arguments are contradicted by the language of the challenged orders and by the tariff provisions that FERC has required ISO-NE to implement.

FERC’s brief fails to address the operative sentence in the Rehearing Order where, although purporting to clarify otherwise, FERC confirms that it is, in fact, requiring a substantive outcome:

We . . . provide clarification that, if ISO-NE determines that there is not a more efficient or cost-effective solution to transmission needs driven by public policy requirements in the regional transmission planning process, ISO-NE need not select a transmission project in the regional transmission plan for purposes of cost allocation.

Rehearing Order at P 126, R. 101 at 60.

The States explained in their initial brief (at 29-30) that, despite FERC’s circuitous language, there is only one reasonable interpretation of this ruling: FERC permits ISO-NE not to select a project only if ISO-NE finds there is not a more efficient or cost-effective transmission solution (i.e., when a local transmission solution is determined to be more efficient or cost-effective than the regional solution).[3]  In every other circumstance, ISO-NE must select a project to meet a public policy objective.  Moreover, whether a regional project or local transmission alternative is selected as the solution to a public policy-driven need, a substantive outcome must be reached.  Such a result is divorced from the process-only description of Order No. 1000 that FERC characterizes earlier in its brief (at 11, 14), and upon which this Court relied in upholding Order No. 1000.[4]  See States Br. at 28-29 (citing South Carolina, 762 F.3d at 89, 91).

FERC asserts that it explicitly rejected in the Rehearing Order any interpretation that it mandated project selection (Br. at 59, citing to Rehearing Order at P 126, R. 101 at 60), citing a particular sentence of the order.  But that sentence cannot be read in isolation.  FERC’s cited language immediately follows the “clarifying” declaration of Paragraph 126 discussed above, which, as explained, can only be read to require ISO-NE to select a project for inclusion in the Regional System Plan, unless a local project is found to be more efficient or cost-effective—in either case, a substantive outcome.

FERC’s claim that it is not requiring project selection is belied by the public policy planning structure that FERC mandated for New England.  FERC acknowledges that it “directed the filing parties to submit a compliance filing to modify the process for public policy-driven projects.”  Br. at 18.  This included removing NESCOE’s proposed role in identifying “potential public policy-driven solutions that it would like to have further evaluated” and instead requiring that ISO-NE be the entity that selects projects.  Id. at 22.  However, FERC fails to acknowledge that its rulings have established a process that inevitably culminates in a substantive outcome:  (1) once transmission needs driven by public policy requirements are identified, ISO-NE studies potential solutions to meet those needs;[5] (2) once the study is complete, ISO-NE issues a solicitation for projects to meet the public policy needs;[6] (3) after evaluating the responses to the solicitation, ISO-NE identifies the most efficient or cost-effective solution to that need;[7] and (4) in the absence of an alternative local project that is more efficient or cost-effective, ISO-NE will “include the project as a Public Policy Transmission Upgrade in the Regional System Plan.”[8]

As ISO-NE has acknowledged, inclusion in the Regional System Plan has meaning: It entitles a project to regional cost allocation and thus is a material and required step towards construction.  See States Br. at 8 (citing Compliance Filing, R. 1 at 9).  Indeed, a project developer invests in and works through the prolonged ISO-NE process for the purpose of being selected and included in the Regional System Plan.  FERC, nonetheless, ignores the significance of a project being placed in New England’s Regional System Plan.  See Br. at 11 (“Nothing in Order No. 1000 . . . requires that a facility in a regional plan be built.”), 61.  The States explained how placing a project in New England’s Regional System Plan “is a critical and material step toward project financing and construction, allowing the costs of a project to be recovered from all customers taking regional network service under the ISO-NE OATT and triggering a series of next steps including application for state siting review.”  States Br. at 36 (footnote omitted); see also id. at 7-9, 36.  FERC, however, fails to confront this direct nexus between the operation of New England’s Regional System Plan and project construction.  Under the structure FERC has required, once the evaluation process commences, it essentially acts on autopilot through selection of a project for purposes of cost allocation and inclusion in the Regional System Plan.

Once ISO-NE places a project in the Regional System Plan based on its judgment of state policy requirements, states may be forced to be more cautious about pursuing other more cost-effective non-transmission approaches to meeting policy requirements.  Even if less expensive options were available, with a pending ISO-NE transmission solution, there would be concern about increasing overall costs to consumers by having duplicate solutions to meet the same need.

The States have explained that ISO-NE, the entity that FERC charged with implementing the public policy planning process, shared the States’ view that the Compliance Order expanded the requirements of Order No. 1000 by imposing an obligation to select projects.  States Br. at 27 (citing R. 57 at 55).  Certainly, other interests, particularly those that stand to gain millions or billions of dollars through project development, will press the same interpretation absent a definitive ruling from FERC, on remand, that it is requiring only what this Court interpreted as the Order No. 1000 mandate, i.e., “processes for identifying and evaluating public policies that might affect transmission needs” (South Carolina, 762 F.3d at 91 (emphasis in original)), and nothing more.

II.           FERC’s Undisputed Authority over Interstate Transmission Planning and Cost Allocation Does Not Give FERC License to Decide how State Policies Should Be Implemented.

The rules under review require ISO-NE to make judgments about how state policies are to be executed.  As the States have explained, this ruling represents an unlawful encroachment into state authority.  It exceeds the limits of FERC’s jurisdiction under the FPA, 16 U.S.C. § 791a, et. seq., and implicates the constitutional boundaries of federal authority.  States Br. at 34-43.

FERC takes two approaches in an attempt to rebut the States’ claim, neither of which demonstrates that the FPA grants FERC the power to implement state policies or to direct ISO-NE to supplant states’ decision-making regarding the most efficient or cost-effective way to implement state policies.

A.           Contrary to FERC’s Characterization, the Challenged Orders Require ISO-NE Selection of Transmission Projects to Meet State Public Policy Needs, Thus Requiring Substantive Outcomes and Infringing on State Authority.

FERC doubles down on its claim that the challenged orders required only a “consideration” of policy-driven transmission needs.  Br. at 60-62.  It states that “ISO New England would not make judgments about state policies or the means by which States would satisfy their policy objectives; rather, it would consider ‘only transmission needs driven by public policy requirements’ – ‘a role appropriate for its function as a regional transmission organization and independent system operator.’”  Id. at 61-62 (emphasis in original) (quoting Rehearing Order at P 133, R. 101 at 64).  But as explained above and in the States’ initial brief (at 7-9, 30-31), the effect of the changes mandated by the orders under review is that, once the process for evaluating potential solutions commences, ISO-NE is ultimately required to select a project.  Once the “go” button is pressed on the study process, in light of FERC’s rulings, an ISO-NE-selected project will be placed in the Regional System Plan except in the unlikely event a local alternative is found to be more efficient or cost-effective.  Thus, FERC’s contention that the challenged orders only require ISO-NE to “consider” policy-driven transmission needs is not accurate.

Selecting a transmission project on the basis that it is the most efficient and cost-effective transmission solution to meet a state public policy requirement is making a judgment about the best means to satisfy that particular state’s law or regulation.  Such selection requires a choice of one specific type of infrastructure solution to satisfy a state’s public policy.  Once the transmission solution is selected, other non-transmission and non-utility related solutions may be precluded.  For example, as illustrated in the States’ initial brief (at 38-39), some states have set greenhouse gas limits as a matter of public policy, reflected in those states’ laws.  Based on this identified public policy, ISO-NE may study transmission projects to interconnect with clean energy resources (e.g., wind) and determine which of those projects is the most efficient or cost-effective.  However, that solution would fail to account for other mechanisms a state might prefer to pursue to achieve its emissions reductions, such as more proximate distributed generation (e.g., solar) or solutions through non-energy sectors (e.g., transportation and buildings).

As discussed above (supra at 9), ISO-NE’s placement of a project in the Regional System Plan could limit a state’s ability to pursue other, less costly options.  A state’s preferred solution to address its own public policy requirements may be based on how the solution interacts with and advances other state policies as well, such as economic development, job growth, tax revenue, remediation of underutilized lands, and so forth.  The state’s preferred solution may not include a transmission project at all, notwithstanding that ISO-NE may have found a particular transmission project to be more efficient or cost-effective than others.  The act of selecting a transmission project to move forward requires ISO-NE inevitably to substitute its judgment for that of state authorities over how to best implement a particular state’s public policies.

The structure required by FERC in the challenged orders unlawfully relegates that state to the same non-decisional role in ISO-NE’s public policy transmission planning process accorded to private sector stakeholders in New England.  The Court should not permit this overstepping of FERC’s authority.  Neither ISO-NE nor FERC is designated by states to implement state laws or regulations, and the FPA provides no such authority.

States’ authority in connection with state public policy does not begin and end with “developing” or “setting” policies, as FERC suggests.  See Br. at 23 (“States continue to be able to exercise their traditional authority to develop public policy . . . .”), 60 (“The Commission . . . appropriately respected the States’ prerogative to set public policy . . . .”).  States undeniably have the authority and obligation to implement their own public policies as well.  FERC focuses on the fact that Order No. 1000 has left to states the ability to develop and set public policies.  Its argument ignores that after state legislatures develop and set policies, it is the essential function of the executive branch of state governments to execute them.  FERC’s claim to respect state authority by respecting only a state’s ability to develop public policies – and overlooking a state’s ability to execute those policies – reflects a deeply flawed and unsupported view of the constitutional obligations of the executive branch of state governments and the demarcation between federal and state jurisdiction.

FERC’s claim that it “appropriately respected the States’ prerogative to set public policy and their traditional authority over siting, permitting, and construction of transmission facilitates” (Br. at 60; see also id. at 23, 61) misses the mark.  The States have not asserted that the challenged orders invade those specific state authorities.  FERC’s claim is a distraction from the narrow inquiry at issue in this case, i.e., whether, by requiring ISO-NE to select specific projects to satisfy public policies, the orders on review exceed the bounds of FERC’s authority.  FERC’s brief never comes to grips with the argument made by the States.

To the extent that FERC’s implication (Br. at 23, 61) is that the existence of state authorities such as denying permits or siting approval constitutes a “silver bullet” that states can use if they disagree with a state public policy-driven project that ISO-NE selects, the States have already corrected this misinterpretation.  The States explained that:

There is no assurance whatsoever of alignment between the location of an ISO-NE-selected transmission upgrade to meet a state’s policy objectives and that state’s siting jurisdiction.  In other words, while State A could choose not to site transmission within its boundaries, there is no certainty that a transmission project that ISO-NE selects to meet State A’s policy needs would be located within State A’s borders and thus subject to its permitting requirements.  Accordingly, the project ISO-NE selects in furtherance of State A’s policy objectives might still move forward even if state officials in State A object to such project on economic, environmental or other grounds, and State A’s consumers would still be responsible for paying for a portion of the ISO-NE preferred transmission upgrades.

States Br. at 37.  FERC does not rebut this potential outcome in its response.

Similarly, FERC’s suggestion that NESCOE’s role in identifying policies that drive transmission needs should mitigate the States’ concerns about FERC requiring ISO-NE to select state public policy-driven transmission projects (Br. at 61) is unpersuasive.  As a threshold matter, affording the states a role in policy identification does not justify FERC expanding its authority by requiring ISO-NE to select state-policy driven transmission projects.  Nor does it cure the need for FERC to provide notice and opportunity to comment before expanding the scope of a final rule.  See States Br. at 31-33.  In any case, NESCOE’s request for a study is just that – it is a request for information about the costs of potential transmission projects, not the endorsement of any particular project.  As explained above, a state with policies at issue may ultimately not view any transmission project as its preferred means to advance a given state policy, but under FERC’s process, ISO-NE would nonetheless be required to select a project, as long as it is found to be more efficient or cost-effective than a local transmission solution.

B.            FERC’s Authority Over Interstate Transmission and Cost Allocation Does Not Grant FERC the Authority to Determine How to Implement State Public Policies.

FERC argues that if “the States are claiming that they must be entitled to determine whether to select a project for cost allocation purposes . . . that contention is without merit.”  Br. at 62 (citation omitted).  The States make no such claim.  What the States contend is that the process FERC established in the orders on review results in ISO-NE selecting a transmission project in the Regional System Plan for purposes of cost allocation that is intended to meet the requirements of a state’s laws or regulations, and that this process[9] exceeds the scope of Order No. 1000 and exceeds FERC’s authority.

The States recognize FERC’s jurisdiction over interstate transmission.  See, e.g., States Br. at 41-42 (“The States do not challenge FERC’s authority over interstate transmission . . . . Nor do the States challenge FERC’s authority to direct transmission providers to engage in transmission planning for public policies in general.”).  The States ask that FERC likewise respect states’ fundamental authority over decisions about whether, how and at what cost to execute their own laws.  Order No. 1000 only concerned process (i.e., consideration—identification and evaluation of—public policy requirements that drive transmission) and purported not to dictate any substantive outcomes.  The rulemaking did not address the appropriate role of state officials in the context of selecting public policy-driven projects.  Instead, FERC determined that the specific role that state officials would play in considering how public policies drive transmission could be addressed in the compliance filings.  See Br. at 57-58.  For New England, however, FERC rejected ISO-NE’s proposed approach to project selection whereby NESCOE and/or state regulatory authorities would submit a “public policy transmittal” as a pre-condition for ISO-NE’s selecting a policy-driven transmission project for placement in the Regional System Plan.  Instead, FERC expanded Order No. 1000 beyond process (see States Br. at 17-18), and in so doing, failed to give the states any meaningful role in the selection of projects studied to satisfy transmission needs stemming from their own public policies.

The FPA does not confer on FERC authority to decide how to implement state laws.  States Br. at 34-43 (citing Section 201(a), 16 U.S.C. § 824(a)).  FERC misreads South Carolina to the extent it believes that the Court has countenanced such an intrusion.  See Br. at 62-63.  First, South Carolina validates the States’ understanding of the Order No. 1000 requirements, with the Court holding that the FERC rule “merely require[s] regions to establish processes for identifying and evaluating public policies that might affect transmission needs.” South Carolina, 762 F.3d at 91 (emphasis in original); see also id. at 89.  Second, contrary to FERC’s claim (Br. at 62), the arguments the Court rejected in South Carolina are inapposite to the current proceeding.  Petitioners in South Carolina challenged FERC’s authority over transmission planningSee id. at 63-64.  The States have not petitioned this Court for review of that authority.  As stated above, the States do not contest that FERC may require transmission planning for public policies in general.  See supra at 16; see also States Br. at 41-42.  Indeed, before FERC rewrote the rules during the compliance phase, NESCOE had been generally supportive of this planning process reform as it was originally articulated by FERC.  See States Br. at 10, 42.  The States’ petition only concerns FERC’s unlawful expansion of its final rule and the imposition of an obligation on ISO-NE to select projects that that ISO-NE concludes are designed to meet public policy needs.

Similarly, FERC’s oversight over transmission cost allocation (see FERC Br. at 63) does not provide authority for FERC to require that ISO-NE select transmission projects to meet state public policy needs, thus choosing the specific way in which one or more state’s policies will be implemented.  First, as a point of fact, cost allocation is triggered after project selection.  Before ISO-NE can apply cost allocation to a project, it must first select a project as the solution to a state public policy need.  Second, the States are not challenging FERC’s authority over interstate transmission rates (see Br. at 41-42), and such a line of argument is irrelevant to the core issues in this proceeding.

FERC’s reference to two recent Supreme Court cases is also unavailing.  As support for its argument that it has broad authority over transmission, FERC cites FERC v. Elec. Power Supply Ass’n, 136 S. Ct. 760 (2016) (“EPSA”) and Oneok, Inc. v. Learjet, Inc., 135 S. Ct. 1591 (2015) as standing for the proposition that federal and state jurisdiction may overlap.  Br. at 62-63.  FERC’s next stroke of the pen, however, contradicts this view.  FERC effectively argues that its jurisdiction over transmission rates provides authority to determine, solely and without any state role, the appropriate means to execute state laws.  Br. at 63 (asserting that jurisdiction over cost allocation sanctions FERC’s rulings).  Such an outcome runs contrary to EPSA and Oneok.

The demand response program in EPSA stands in sharp contrast to the structure for state public policy-driven transmission projects that FERC has mandated through the orders on review.  Under that demand response program, FERC allowed states “veto power” over demand response participation in the wholesale market “in recognition of the linkage between wholesale and retail markets and the [s]tates’ role in overseeing retail sales.”  EPSA, 136 S. Ct. at 779.   The Supreme Court characterized this arrangement as “cooperative federalism, in which the [s]tates retain the last word.”  Id. at 780; see also id. at 776 (noting that wholesale and retail markets “are not hermetically sealed from each other”).  The challenged orders represent a retrenchment from this ideal of “cooperative federalism,” as FERC’s rulings exceed the agency’s authority by directing ISO-NE to take actions that constitute determinations about the best way to advance a state public policy.  Likewise, in holding that state antitrust claims were not preempted by the Natural Gas Act, the Supreme Court rejected in Oneok the notion that there was a “clear division between areas of state and federal authority in natural-gas regulation.”  135 S. Ct. at 1601.

In examining its own authority over interstate transmission, FERC is not heeding this principle of cooperative federal and state jurisdiction.  It turns the ruling in EPSA on its head: By removing any role for states in the project evaluation process, FERC has given ISO-NE a veto over a state official’s decision regarding whether, how and at what cost to satisfy a state policy need.  Through the challenged orders, FERC creates a new jurisdictional line, which did not exist in Order No. 1000, whereby its regulation of transmission empowers FERC to make state policy implementation decisions.

CONCLUSION

The States reiterate that FERC could remedy the deficiencies of the orders on review by issuing in the proceeding below a definitive statement that (1) ISO-NE is not required to select a policy-driven transmission project and, consistent with FERC’s prior declarations, is only required to identify needs and evaluate potential solutions, and (2) ISO-NE has no authority to substitute its judgment for a state whose laws are at issue in selecting a project.  States Br. at 25.  For the reasons discussed above and in their initial brief, the States respectfully request that the Court vacate the relevant aspect of the orders and remand the case to FERC.

Respectfully submitted,

New England States Committee on Electricity, Inc.:

/s/ Phyllis G. Kimmel
John Michael Adragna
Phyllis G. Kimmel
Jeffrey K. Janicke
McCarter & English, LLP
1015 Fifteenth Street, N.W.
Twelfth Floor
Washington, DC 20005
(202) 753-3400
pkimmel@mccarter.com

/s/ Jason Marshall
Jason Marshall
General Counsel
New England States Committee on Electricity, Inc.
655 Longmeadow Street
Longmeadow, MA 01106
(617) 913-0342
jasonmarshall@nescoe.com

Attorneys for the New England States Committee on Electricity, Inc.

Connecticut Department of Energy and Environmental Protection:

/s/ Robert Snook
Robert Snook, AAG
Office of the Attorney General
Ten Franklin Square
New Britain, CT 06051
(860) 827-2657
Robert.Snook@ct.gov

Attorney for the Connecticut Department of Energy and Environmental Protection

Connecticut Public Utilities Regulatory Authority:

/s/ Clare Kindall
Clare Kindall, AAG
Department Head – Energy
Office of the Attorney General
Ten Franklin Square
New Britain, CT 06051
(860) 827-2683
Clare.kindall@ct.gov

Attorney for the Connecticut Public Utilities Regulatory Authority

Massachusetts Department of Public Utilities:

/s/ Jeffrey M. Leupold
Maura Healey, Massachusetts Attorney General
Cecile M. Fraser, Counsel
Special Assistant Attorney General
Jeffrey M. Leupold, Senior Counsel
Massachusetts Department of Public Utilities
One South Station, Fifth Floor
Boston, MA 02110
(617) 305-3621
Cecile.Fraser@state.ma.us
Jeffrey.Leupold@state.ma.us

Attorneys for the Massachusetts Department of Public Utilities

New Hampshire Public Utilities Commission:

/s/ F. Anne Ross
Anne Ross
General Counsel
New Hampshire Public Utilities Commission
21 South Fruit Street, Suite 10
Concord, New Hampshire 03301-2429
(603) 271-2431
f.anne.ross@puc.nh.gov

Attorney for the New Hampshire Public Utilities Commission

Rhode Island Public Utilities Commission:

/s/ Leo J. Wold
Leo J. Wold
Assistant Attorney General
150 South Main Street
Providence, RI 02903
(401) 274-4400, ext. 2218
lwold@riag.ri.gov

Attorney for the Rhode Island Public Utilities Commission

Vermont Department of Public Service:

/s/  Edward McNamara
Edward McNamara
Regional Policy Director
Vermont Department of Public Service
112 State Street
Montpelier, VT 05620
(802) 828-4007
ed.mcnamara@state.vt.us

Attorney for the Vermont Department of Public Service

Dated: April 22, 2016

 

Contact InformationCase Number/sService Preference
Carol Jayne Banta
Federal Energy Regulatory Commission
(FERC) Office of the Solicitor
888 First Street, NE
Washington, DC 20426
Email: Carol.Banta@ferc.gov
15-1139
15-1141
Email
Gunnar Birgisson
Florida Power & Light Company
220
801 Pennsylvania Avenue, NW
Suite 220
Washington, DC 20004-0000
Email: gunnar.birgisson@nexteraenergy.com
15-1139Email
Charles GColeon Cole
Steptoe & Johnson LLP
1330 Connecticut Avenue, NW
Washington, DC 20036-1795
Email: ccole@steptoe.com
15-1141Email
Michael Ray Engleman
Squire Patton Boggs (US) LLP
2550 M Street, NW
Washington, DC 20037-1350
Email: michael.engleman@squirepb.com
15-1139Email
Jason J. Fleischer
Gibson, Dunn & Crutcher LLP
1050 Connecticut Avenue, NW
Washington, DC 20036-5306
Email: jfleischer@gibsondunn.com
15-1139
15-1141
Email
Mary Ellen Grover
NSTAR Electric & Gas Corporation
800 Boylston Street
P1700
Boston, MA 02199-8003
Email: mary.grover@nstar.com
15-1139
15-1141
Email
Kenneth G. Jaffe
Alston & Bird LLP
The Atlantic Building
950 F Street, NW
Washington, DC 20004-1404
Email: kenneth.jaffe@alston.com
15-1139
15-1141
Email
Jeffrey Martin Jakubiak
Gibson, Dunn & Crutcher LLP
200 Park Avenue
New York, NY 10166-0193
Email: jjakubiak@gibsondunn.com
15-1139
15-1141
Email
Phyllis E Lemell
Eversource Energy
107 Selden Street
Berlin, CT 06037-0000
Email: phyllis.lemell@eversource.com
15-1139
15-1141
Email
Paul Alessio Mezzina
King & Spalding LLP
1700 Pennsylvania Avenue, NW
Suite 200
Washington, DC 20006-4706
Email: pmezzina@kslaw.com
15-1139Email
Gary Arthur Morgans
Steptoe & Johnson LLP
1330 Connecticut Avenue, NW
Washington, DC 20036-1795
Email: gmorgans@steptoe.com
15-1141Email
Ashley Charles Parrish
King & Spalding LLP
1700 Pennsylvania Avenue, NW
Suite 200
Washington, DC 20006-4706
Email: aparrish@kslaw.com
15-1139Email
David Russell Poe
Bracewell LLP
2001 M Street NW
Suite 900
Washington, DC 20036
Email: david.poe@bracewelllaw.com
15-1139
15-1141
Email
David Barry Raskin
Steptoe & Johnson LLP
1330 Connecticut Avenue, NW
Washington, DC 20036-1795
Email: draskin@steptoe.com
15-1139
15-1141
Email
S. Mark Sciarrotta
VT Transco, Vermont Electric Power Company
366 Pinnacle Ridge Road
Rutland, VT 05701
Email: msciarrotta@velco.com
15-1139
15-1141
Email
Robert Harris Solomon
Federal Energy Regulatory Commission
(FERC) Office of the Solicitor
Room 9A-01
888 First Street, NE
Washington, DC 20426
Email: robert.solomon@ferc.gov
15-1139
15-1141
Email
Stephen Matthew Spina
Morgan, Lewis & Bockius LLP
1111 Pennsylvania Avenue, NW
Washington, DC 20004-2541
Email: sspina@morganlewis.com
15-1139
15-1141
Email
David G. Tewksbury
King & Spalding LLP
1700 Pennsylvania Avenue, NW
Suite 200
Washington, DC 20006-4706
Email: dtewksbury@kslaw.com
15-1139Email
Michael E. Ward
Alston & Bird LLP
The Atlantic Building
950 F Street, NW
Washington, DC 20004-1404
Email: michael.ward@alston.com
15-1139
15-1141
Email

 

Document Source Citations

[1] Reference in this brief to “local” projects, alternatives, or solutions describes projects considered through a single utility’s (and not ISO-NE’s) transmission planning process.  See States Br. at 16 (ISO-NE has planning authority over higher voltage regional transmission facilities serving the whole New England region, while each individual public utility owner in New England has planning authority over lower voltage local transmission facilities serving its utility’s customers or connecting electrical power resources to the regional system).

[2] Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities, Order No. 1000, FERC Stats. & Regs. ¶ 31,323, 76 Fed. Reg. 49,842 (Aug. 11, 2011) (“Order No. 1000”), order on reh’g, Order No. 1000-A, 139 FERC ¶ 61,132, 77 Fed. Reg. 32,184 (May 31, 2012) (“Order No. 1000-A”), order on reh’g and clarification, Order No. 1000-B, 141 FERC ¶ 61,044, 77 Fed. Reg. 64,890 (Oct. 24, 2012), aff’d sub nom. S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41 (D.C. Cir. 2014) (“South Carolina”).

[3] As the States explained, this “off-ramp” is essentially non-existent in New England given the fact that the ISO-NE regional planning process was expressly designed to identify regional facilities that were more efficient or cost-effective than local projects.  Br. at 30-31; see also id. at 15-16.

[4] As noted in the States’ initial brief (at 10, 42), NESCOE did not oppose these procedural reforms to the transmission planning process as FERC had originally articulated them.

[5] Pursuant to Section 4A.2 of the public policy planning process, ISO-NE prepares a proposed scope for the public policy transmission study, and pursuant to Section 4A.3, ISO-NE performs the initial phase of the public policy transmission study.  See R. 68 at 177.

[6] Pursuant to Section 4A.4, ISO-NE provides the results of the public policy transmission study to qualified transmission project sponsors for their use in preparing stage-one proposals to develop the project(s).  R. 68 at 178.  Pursuant to Section 4A.5, ISO-NE performs a preliminary feasibility review of each proposal, and lists the stage-one proposals that meet specified criteria.  R. 68 at 178-181.

[7] Pursuant to Section 4A.7, ISO-NE reports the preliminary stage-two solutions to the planning advisory committee.  R. 68 at 182-183.  Pursuant to Section 4A.8(a), ISO-NE’s identification of the preferred solution “will select the project that best addresses the identified Public Policy Requirement while utilizing the best combination of electrical performance, cost, future system expandability and feasibility to meet the need in the required timeframe.”  R. 68 at 183.

[8] See Section 4A.8 (a), R. 68 at 183.

[9] As the States explained, the process that FERC rejected in the Compliance Orders was one that did not require ISO-NE to select a project at the conclusion of the study process and competitive solicitation.  States Br. at 17 (citing R. 1 at 60 (the process “permits, but does not require, projects to be . . . added to the Regional System Plan for construction.”)).